=表示未激活请求 |
Queue Position | Request Date | Request Status | 业务类型(NR或ER) | Location | Max Summer output | Max Winter output | 互连设备 | 预计投入使用日期 | 设备类型(联合循环、煤、CT、燃料型) |
---|---|---|---|---|---|---|---|---|---|
138 | 5/19/2023 | Feasibility Study | ERIS/NRIS | King County, WA | 175 MW | 175 MW | 黑钻石115kV变电站 | 6/1/2025 | BESS |
137 | 11/10/2022 | System Impact Study | ERIS/NRIS | Columbia County, WA | 150 MW | 150 MW | 初级:Dodge Junction 230 kV变电站备用Phalen Gulch 230 kV变电站 | 4/28/2025 | Solar |
136 | 10/24/2022 | Withdrawn | ERIS/NRIS | King County, WA | 150 MW | 150 MW | Lat = 47.321872 Long = -122.0073 |
12/31/2025 | BESS |
135 | 10/14/2022 | System Impact Study | ERIS/NRIS | 科尔strip和Rosebud县,MT | 800 MW | 800 MW | Colstrip 500kv变电站 | 12/1/2025 | Solar & BESS |
134 | 8/31/2022 | Withdrawn | ERIS/NRIS | Thurston County, WA | 100 MW | 100 MW | 47° 1'29.35"N, 122°57'18.26"W | 12/31/2025 | BESS |
133 | 5/19/2022 | Facilities Study | NRIS | Garfield County, WA | 300 MW | 300 MW | 道奇交界处230千伏变电站 | 12/15/2025 | Solar |
132 | 5/19/2022 | Facilities Study | NRIS | Thurston County, WA | 127 MW | 127 MW | 建议新建115千伏变电站在托诺-布鲁玛尔或托诺-普林恩线路上 | 6/15/2025 | BESS |
131 |
2/23/2022 | Withdrawn | ERIS/NRIS | Garfield County, WA | 197.7755 MW | 197.7755 MW | 道奇交界处230千伏变电站 | 10/31/2024 | Wind |
130 |
2/3/2022 | Withdrawn | ERIS/NRIS | Garfield County, WA | 140 MW | 140 MW | 道奇交界处230千伏变电站 | 9/30/2025 | Wind |
129 |
12/23/2021 | Facilities Study | NRIS | Kitsap County, WA | 200 MW | 200 MW | Foss Corner 115 kV | 12/15/2023 | BESS |
128 | 11/19/2021 | Facilities Study | ERIS | Wheatland and Meagher County, MT | 750 MW | 750 MW | 拟议在Broadview和Townsemd之间新建500千伏开关站 | 10/31/2026 | Wind |
127 | 11/4/2021 | Facilities Study | NRIS | Skagit County, WA | 100 MW | 100 MW | 弗雷多尼亚115千伏变电站 | 12/1/2025 | BESS |
126 | 9/10/2021 | Withdrawn | ERIS/NRIS | Garfield County, WA | 140 MW | 140 MW | Dodge Junction 230 kV Substation | 5/12/2025 | Wind |
125 | 8/31/2021 | Facilities Study | NRIS | Lewis County, WA | 170 MW | 170 MW | Tono 115 kV Substation | 4/1/2026 | BESS |
124 | 8/27/2021 | Draft LGIA | NRIS | Pierce County, WA | 85 MW | 85 MW | Frederickson 115 kV Substation | 9/25/2025 | BESS |
123 | 8/27/2021 | Draft LGIA | NRIS | Garfield County, WA | 150 MW | 150 MW | Phalen Gulch 230 kV Substation | 12/31/2024 | Solar + Storage |
122 | 8/25/2021 | Withdrawn | NRIS | Kitsap County, WA | 125 MW | 125 MW | 南布雷默顿115kV变电站 | 7/1/2024 | BESS |
121 | 8/25/2021 | Draft LGIA | NRIS | King County, WA | 125 MW | 125 MW | Starwood 115 kV | 7/1/2024 | BESS |
120 | 8/25/2021 | Withdrawn | ERIS/NRIS | Whatcom County, WA | 15 MW | 15 MW | 布莱恩115千伏变电站 | 7/1/2024 | BESS |
119 | 8/25/2021 | Facilities Study | NRIS | Columbia County, WA | 150 MW | 150 MW | 道奇交界处230千伏变电站 | 3/31/2024 | solar |
118 | 8/25/2021 | Withdrawn | NRIS | Thurston County, WA | 100 MW | 100 MW | Rochester 115 kV | 9/1/2024 | BESS |
117 | 8/25/2021 | Withdrawn | ERIS/NRIS | Kittitas County, WA | 150 MW | 150 MW | 拟在瀑布-岩石达230千伏线路上新建变电站 | 9/20/2025 | Solar & Storage |
116 | 8/25/2021 | Withdrawn | ERIS/NRIS | Kittitas County, WA | 300 MW | 300 MW | 拟在瀑布-岩石达230千伏线路上新建变电站 | 9/20/2025 | Solar & Storage |
115 | 8/19/2021 | Draft LGIA | NRIS | Columbia County, WA | 140 MW | 140 MW | Dodge Junction 230 kV Substation | 12/1/2025 | BESS |
114 | 7/27/2021 | Draft LGIA | NRIS | Kitsap County, WA | 218.76 MW | 218.76 MW | 备选方案:拟议沿南布雷默顿新建115千伏变电站-布雷默顿115千伏变电站 | 12/1/2024 | Simple-cycle |
113 | 7/27/221 | Draft LGIA | ERIS | Lewis County, WA | 218.78 MW | 218.78 MW | 主要:在托诺、布鲁马尔和罗切斯特变电站之间拟议新建115千伏变电站 | 10/15/2025 | Simple-cycle |
112 | 6/23/2021 | Draft LGIA | NRIS | Thurston County, WA | 127 MW | 127 MW | 提议在托诺、布鲁梅尔和罗切斯特变电站之间新建115千伏变电站 | 6/15/2025 | BESS |
111 | 6/23/2021 | Withdrawn | ERIS/NRIS | Kitsap County, WA | 20 MW | 20 MW | Foss Corner 115 kV | 12/15/2023 | BESS |
110 | 6/18/2021 | Draft LGIA | NRIS | Garfield County, WA | 150 MW | 150 MW | 法伦峡谷230千伏变电站 | 12/31/2024 | Solar & Storage |
109 | 5/27/2021 | Draft LGIA | NRIS | Kitsap County, WA | 200 MW | 200 MW | 南布雷默顿115kV变电站 | 12/15/2023 | BESS |
108 | 4/20/2021 | Withdrawn | ERIS/NRIS | Skagit County, WA | 200 MW | 200 MW | 弗雷多尼亚115千伏变电站 | 6/1/2023 | BESS |
107 | 4/20/2021 | Withdrawn | ERIS/NRIS | Pierce County, WA | 200 MW | 200 MW | 白河115千伏变电站 | 6/1/2023 | BESS |
106 | 4/20/2021 | Withdrawn | ERIS/NRIS | Lewis County, WA | 200 MW | 200 MW | Tono 115-kV Substation | 6/1/2023 | BESS |
105 | 4/20/2021 | Draft LGIA | ERIS | Skagit County, WA | 200 MW | 200 MW | Sedro Wooley 230千伏变电站 | 6/1/2023 | BESS |
104 | 4/16/2021 | Withdrawn | ERIS/NRIS | Whatcom County, WA | 200 MW | 200 MW | 115千伏变电站 | 6/1/2023 | BESS |
103 | 4/15/2021 | Draft LGIA | NRIS | King County, WA | 200 MW | 200 MW | Sedro Wooley 230千伏变电站 | 1/6/2024 | BESS |
102 | 4/15/2021 | Draft LGIA | NRIS | Skagit County, WA | 150 MW | 150 MW | St. 克莱尔230千伏变电站 Tono 115 kV |
1/6/2024 | BESS |
101 | 4/15/2021 | Draft LGIA | NRIS | King County, WA | 200 MW | 200 MW | Berydale 230千伏变电站 | 1/6/2024 | BESS |
100 | 4/15/2021 | Draft LGIA | NRIS | Pierce County, WA | 200 MW | 200 MW | 白河115千伏变电站 | 1/6/2024 | BESS |
99 | 4/15/2021 | Draft LGIA | NRIS | King County, WA | 250 MW | 250 MW | 塔尔博特山230千伏变电站 | 6/1/2025 | BESS |
98 | 3/19/2021 | Draft LGIA | NRIS | Pierce County, WA | 200 MW | 200 MW | White River 230kV | 12/15/2023 | Battery/Inverter |
97 | 1/20/2021 | LGIA | ERIS | Rosebud & Treasure Counties, MT | 300 MW | 300 MW | Colstrip变电站500kV | 12/31/2024 | Wind |
96 | 1/20/2021 | LGIA | ERIS | Rosebud, Treasue & Bighorn Counties, MT | 300 MW | 300 MW | Colstrip变电站500kV | 12/31/2024 | Wind |
95 | 1/20/2021 | LGIA | ERIS | Rosebud, Treasue & Bighorn Counties, MT | 300 MW | 300 MW | Colstrip变电站500kV | 12/31/2024 | Solar |
94 | 1/22/2021 | Facilities Study | ERIS | Meagher County, MT | 326.25 MW | 326.25 MW | 拟议在Broadview和Townsend之间新建500kV变电站 | 12/31/2024 | Wind |
93 (Merchant) |
12/22/2020 | Withdrawn | ERIS | Skagit County, WA | 63 MW | 63 MW | Shannon Substation | 7/1/2022 | Hydro |
92 | 12/17/2020 | In-Service/SGIA | NA | King County, WA | 6.5 MW | 6.5 MW | 斯诺夸尔米开关站 | Hydro | |
91 | 12/17/2020 | In-Service/SGIA | NA | King County, WA | 6.5 MW | 6.5 MW | 斯诺夸尔米开关站 | Hydro | |
90 |
在申请阶段撤回 | ||||||||
89 | 8/19/2020 | Withdrawn | ERIS | Thurston County, WA | 100 MW | 100 MW | 机场115千伏变电站 | 12/31/2023 | Storage |
88 | 7/31/2020 | LGIA | ERIS | Wheatland & Meagher Counties, MT | 750 MW | 750 MW | 建议新建变电站 | 10/31/2026 | Wind |
87 | 7/24/2020 | Draft LGIA | NRIS | Skagit County, WA | 100 MW | 100 MW | 弗雷多尼亚115千伏变电站 | 11/30/2023 | Storage |
86 | 7/24/2020 | Draft LGIA | NRIS | Whatcom County, WA | 100 MW | 100 MW | 115千伏变电站 | 11/30/2023 | Storage |
85 | 在申请阶段撤回 | ||||||||
84 | 在申请阶段撤回 | ||||||||
83 | 7/17/2020 | LGIA | NRIS/ERIS | Yellowstone County, MT | 500 MW | 500 MW | Broadview Subsation | 12/31/2023 | 储能、风能和太阳能 |
82 | 5/19/2020 | Withdrawn | ERIS/NRIS | Thurston County, WA | 100 MW | 100 MW | Yelm Substation | 12/31/2022 | Storage |
81 | 4/27/2020 | Draft LGIA | ERIS | Pierce County, WA | 100 MW | 100 MW | 弗雷德里克森电站115kV变电站 | 4/1/2023 | Storage |
80 | 在申请阶段撤回 | ||||||||
79 | 10/22/2019 | Active. 参见西北能源的队列 | ERIS/NRIS | Rosebud County, MT | 500 Mw | 500 Mw | Colstrip 500kv变电站 | 9/1/2024 | Wind & Storage |
78 | 在申请阶段撤回 | ||||||||
77 | 在申请阶段撤回 | ||||||||
76 | 9/9/2019 | LGIA | ERIS | King County, WA | 100 MW | 100 MW | 克里斯托弗115千伏变电站 | 8/13/2025 | Storage |
75 | 9/9/2019 | LGIA | Withdrawn | Douglas County, WA | 250 MW | 250 MW | 建议新建变电站 | 10/31/2022 | Solar |
74 Affiliate: sPower |
7/18/2019 | Withdrawn | ERIS | Douglas County, WA | 160 MW | 160 MW | 白河-岩石达230千伏线路 | 9/1/2023 | Solar & Storage |
73 | 6/19/2019 | LGIA | ERIS | Rosebud & Carter County, MT | 400 MW | 400 MW | Colstrip 500kv变电站 | 12/1/2022 | Wind |
72 | 6/17/2019 | LGIA | ERIS | Rosebud & Carter County, MT | 600 MW | 600 MW | Colstrip 500kv变电站 | 12/1/2022 | Wind |
71 | 3/28/2019 | LGIA | ERIS | Meagher & Wheatland Counties, MT | 300.15 MW | 300.15 MW | Colstrip 500 kV Line | 11/1/2027 | Wind |
70 | 2/14/2019 | LGIA | ERIS/NRIS | Wheatland County, MT | 634.8 MW | 634.8 MW | 拟议在Broadview和Townsend之间新建500kV变电站 | 9/1/2027 | Wind |
69 | 9/20/2018 | Withdrawn | ERIS/NRIS | Skagit County, WA | 46.68 MW | 46.68 MW | Texaco West Substation | 5/24/2019 | CT |
68 | 9/20/2018 | Withdrawn | ERIS/NRIS | Skagit County, WA | 46.68 MW | 46.68 MW | Texaco West Substation | 7/26/2019 | CT |
67 | 9/14/2018 | Withdrawn | ERIS/NRIS | Kittitas County, WA | 80 MW | 80 MW | 级联-岩石到达230kV线路 | 12/31/2020 | Solar |
66 | 8/27/2018 | LGIA | ERIS | 玫瑰花蕾,草原,道森和卡斯特县,MT | 750 MW | 750 MW | Colstrip变电站500kv | 9/1/2021 | Wind |
65 | 8/27/2018 | LGIA | ERIS | 玫瑰花蕾,草原,道森和卡斯特县,MT | 750 MW | 750 MW | Colstrip变电站500kv | 9/1/2021 | Wind |
64 | 8/22/2018 | Withdrawn | NRIS/ERIS | Skagit County, WA | 46.68 MW | 46.68 MW | Texaco West Substation | 10/1/2018 | CT |
63 | 8/16/2018 | Withdrawn | NRIS/ERIS | Thurston County, WA | 105.4 MW | 105.4 MW | Longmire/Yelm/ Blumaer变电站 | 10/31/2022 | Solar |
62 | 8/16/2018 | Withdrawn | NRIS/ERIS | Thurston County, WA | 40 MW | 40 MW | Yelm Substation | 12/31/2020 | Storage |
61 | 8/15/2018 | Withdrawn | NRIS/ERIS | Kitsap County, WA | 200 MW | 200 MW | 南布雷默顿115kV变电站 | 9/30/2022 | Storage |
60 | 8/15/2018 | LGIA | ERIS | Pierce County, WA | 200 MW | 200 MW | 弗雷德里克森电站115kV变电站 | 12/31/2025 | Storage |
59 | 8/2/2018 | Withdrawn | NRIS/ERIS | Pierce County, WA | 150 MW | 150 MW | Alderton 230kV变电站 | 9/1/2022 | Storage |
58 | 1/22/2018 | Withdrawan | NRIS/ERIS | Douglas County, WA | 176 MW | 176 MW | 级联-岩石到达230kV线路 | 12/31/2020 | Solar |
57 | 1/9/2018 | Withdrawn | NRIS | Kittitas County, WA | 35 MW | 35 MW | 级联-岩石到达230kV线路 | 4/9/2020 | Solar |
56 | 1/8/2018 | LGIA | ERIS | Douglas County | 100.6 MW | 100.6 MW | 级联-岩石到达230kV线路 | 12/31/2023 | Solar |
55 | 1/8/2018 | LGIA | ERIS | Douglas County | 100.6 MW | 100.6 MW | 级联-岩石到达230kV线路 | 12/31/2023 | Solar |
54 | 12/27/2017 | LGIA | NRIS | 格雷斯港县,华盛顿州 | 198.8 MW | 198.8 MW | Olympia Substation | 6/1/2026 | 燃气轮机/联合循环 |
53 | 10/17/2017 | Withdrawn | ERIS/NRIS | Thurston county, WA | 180 MW | 180 MW | 托诺-奥林匹亚115千伏线路 | 10/31/2019 | Solar |
52 | 10/16/2017 | Draft LGIA | ERIS | Kittitas County, WA | 20 MW | 20 MW | 瀑布-岩石到达230千伏线路 | 12/31/2025 | Wind |
51 | 9/13/2017 | LGIA | ERIS | Kittitas, County, WA | 79.2 MW | 79.2 MW | 瀑布-岩石到达230千伏线路 | 12/31/2024 | Solar |
50 | 6/26/2017 | Withdrawn | ERIS/NRIS | 刘易斯和瑟斯顿县,华盛顿州 | 17.25 MW | 17.25 MW | Tono Substation | 12/31/2018 | Wind |
49 | 4/25/2017 | Draft LGIA | ERIS | Kittitas County, WA | 100 MW | 100 MW | 风岭230kV变电站 | 12/31/2023 | Solar |
48 | 1/26/2017 | LGIA | NR/ER(仅适用于PSEI) | Yellowstone County, MT | 300 MW | 300 MW | Broadview Subsation | 12/31/2021 | Solar |
47 | 11/30/2016 | LGIA | ER | Meagher County, MT | 450 MW | 450 MW | Colstrip传输系统- 3英里. west of Martinsdale | 2/1/2023 | Hydro Pumped Storage |
46 | 1/19/2016 | LGIA | NRIS | Lewis & Thurston Counties, WA | 136.8 MW | 136.8 MW | Tono Substation | Initial: 12/31/2017 Revised: 12/27/2019 |
Wind |
45 | 10/29/2015 | Draft LGIA | ERIS | Kittitas County, WA | 80 MW | 80 MW | 级联-岩石到达230千伏线路 | 12/31/2025 | Wind |
44 | 12/29/2015 | LGIA/In-Service | ERIS | 玫瑰花蕾,草原和卡斯特县,MT** | 750 MW | 750 MW | Colstrip 500kV变电站 | 10/1/2021 | Wind |
43 (PSE Merchant) |
6/9/2015 | Withdrawn | Whatcom County, WA | 300 kVA | 300 kVA | Glacier 12 | 12/1/2015 | Battery/Inverter | |
42 | 5/14/2015 | Withdrawn | Both | Lewis County, WA | 150 MW | 150 MW | Tono Substation | 12/31/2017 | Wind |
41 (PSE Merchant) |
1/12/2015 | Withdrawn | Whatcom County, WA | 2 MW | 2 MW | Glacier 12 | 12/1/2015 | Battery/Inverter | |
40 | 12/29/2014 | Withdrawn | ER | Meagher County, MT | 600 MW | 600 MW | 叠层传输系统 | 6/1/2019 | Pumped Storage |
39 | 7/22/2014 | SGIA /Terminated | Kitsap County, WA | 1412 kVA | 1412 kVA | Murden Cove 16 | 8/1/2015 | Battery/Inverter | |
38 | 7/23/2013 | Withdrawn | Both | 玫瑰花蕾和卡斯特县,MT** | 300.9 MW | 300.9 MW | Colstrip Substation | 12/1/2016 | Wind |
37 | 8/28/2012 | LGIA /已投入使用 | NR | Skagit County, WA | 40 MW | 20 MW | Terrell Substation | 11/1/2012 | CT |
36 | 11/8/2011 | 可行性研究/撤销 | Both | Snohomish County, WA | 323 MW | 323 MW | sedroo - bothell - horse Ranch或sedroo - horse Ranch 230千伏线路 | 12/1/2015 | CT |
35 (PSE Merchant) |
9/6/2011 | LGIA /已投入使用 | NR | Skagit County, WA | 30.4 MW | 30.4 MW | 贝克河调水站 | 4/1/2013 | Hydro |
34 | 7/1/2011 | 接受SGIA /在役 | ERIS | King County, WA | 6 MW | 6 MW | 斯诺夸尔米开关站 | 11/1/2016 | Hydro |
33 | 7/1/2011 | 接受SGIA /在役 | ERIS | King County, WA | 6 MW | 6 MW | 斯诺夸尔米开关站 | 11/1/2016 | Hydro |
32 | 4/20/2011 | Withdrawn | Both | Kiittitas County, WA | 176.4 | 176.4 | 瀑布-岩石到达230千伏线路 | 9/1/2014 | Wind |
31 (PSE Merchant) |
2/14/2011 | LGIA /已投入使用 | NR | King County, WA | 8.3 MW | 8.3 MW | 斯诺夸尔米开关站 | 2013年3月5日-厂房1号12/11/2102 -厂房2号 | Hydro |
30 (PSE Merchant) |
2/1/2011 | Withdrawn | NR | Skagit County, WA | 205 MW | 232 MW | Fredonia Substation | 12/1/2014 | Gas Turbine |
29 | 2011年1月14日(由于打字错误,日期由2011年11月14日更改) | Withdrawn | NR | Skagit County, WA | 31MW | 31MW | 贝克河调水站 | 1/1/2013 | Hydro |
28 | 11/10/2010 | Withdrawn | NR | Skagit County, WA | 225 MW | 206 MW | Fredonia Substation | 12/1/2014 | Gas Turbine |
27 | 8/19/2010 | Withdrawn | King County, WA | 10 MW | 10 MW | Snoqualmie Switch | 3/1/2013 | Hydro | |
26 | 6/4/2010 | Withdrawn | King County, WA | 5 MW | 5 MW | Snoqualmie Sub | 2016 | Hydro | |
25 | 6/4/2010 | Withdrawn | King County, WA | 5 MW | 5 MW | Snoqualmie Sub | 2016 | Hydro | |
24 | 5/14/2010 | Withdrawn | Both | Jefferson County, WA | 25 MW | 25 MW | 汤森德港1号115kV线路 | 7/15/2012 | Biomass |
23 | 4/13/2010 | Withdrawn | NR | Skagit County, WA | 346 MW | 367 MW | Fredonia Substation | 12/1/2013和12/1/2017 | 燃气轮机/联合循环 |
22 | 3/16/2010 | Withdrawn | Both | Snohomish County, WA | 252 MW | 302 MW | 贝弗利公园变电站 | 11/1/2012 | Gas turbine |
21 | 2/2/2010 | Withdrawn | NR | Skagit County, WA | 200 MW | 200 MW | Fredonia Substation | 6/1/2013 | Gas turbine |
20 | 1/6/2010 | Withdrawn | Both | Pierce County, WA | 340 MW | 340 MW | •弗雷德里克森变电站 | 6/1/2014 | Combined Cycle |
19 | 9/16/2008 | 设施研究/签发LGIA | ER | Wheatland County, MT | 200 MW | 200 MW | Broadview-Townsend 500千伏线路附近的林林,MT | 12/31/2013 | Wind |
18 | 8/12/2008 | In Sevice Accepted | Whatcom County, WA | 600kW | 600kW | 林登配电给料机(lynn -23) | 2009 | Biomass | |
17 | 6/26/2008 | In Service Accepted | NR | Kittitas County, WA | 12 MW | 12 MW | 风岭230kV变电站 | late 2009 | Wind |
16 | 6/6/2008 | Withdrawn | Kittitas County, WA | 9 MW | 9 MW | 野马风脊230kV线路/风脊 | 11/22/2009 | Wind | |
15 | 3/24/2008 | Accepted | Skagit County, WA | 750KW | 750kW | Peths Corner配电馈线(PET-16) | 10/1/2008 | Biomass | |
14 | 3/10/2008 | Withdrawn | ER | Kittitas, County, WA | 190 MW | 190 MW | 瀑布-岩石到达230千伏线路 | 12/1/2009 | Wind |
13 | 9/26/2007 | LGIA | Both | Kittitas County, WA | 103.5 MW | 103.5 MW | 野马风脊230kV线路/风脊 | 11/30/2008 | Wind |
12 | 6/25/2007 | Withdrawn | Both | Kittitas County, WA | 150 MW | 150 MW | 野马风脊230kV线路/风脊 | 9/30/2008 | Wind |
11 | 6/15/2007 | Withdrawn | Both | Kittitas County, WA | 108 MW | 108 MW | 瀑布-岩石到达230千伏线路 | 12/1/2008 | Wind |
10 | 6/8/2007 | In Service Accepted | NR | Skagit County, WA | 85 MW | 85 MW | 贝克河调水站 | 2007 | Hydro |
9 | 4/1/2006 | Customer withdrew | NR | Whatcom County, WA | 610 MW | 610 MW | 靠近PSE Arco变电站 | 4/1/2008 | Combustion Turbine |
8 | 1/13/2006 | Customer withdrew | Both | Pierce County, WA | 287 MW | 309 MW | •弗雷德里克森变电站 | 8/1/2009 | Combustion Turbine |
7 | 12/21/2005 | Customer withdrew | NR | Pierce County, WA | 102 MW | 102 MW | Deringer Substation | 7/30/2007 | Combustion Turbine |
6 | 11/16/2005 | Customer Withdrew | Both | Kittitas County, WA | 100 MW | 100 MW | IP Line | 12/31/2007 | Wind |
5 | 10/17/2005 | In Service Accepted | Both | Kittitas County, WA | 65 MW | 65 MW | IP Line | 10/15/2007 | Wind |
4 | 7/19/2006 | In Service Accepted | NR | Skagit County, WA | 31 MW | 31 MW | 靠近PSE Fredonia变电站 | 12/31/2006 | Biomass |
3 | 5/23/2005 | Customer withdrew | ER | King County, WA | 27 MW | 27 MW | Under Review | 10/1/2007 | LF Gas |
2 | 1/15/2005 | In Service Accepted | ER | Kittitas County, WA | 40 MW | 40 MW | IP Line | 10/1/2005 | Wind |
1 | 8/24/2004 | Customer Withdrew | Whatcom County, WA | 5.5 MW | 5.5 MW | Sumas-Bellingham 115千伏 | 6/1/2006 | Heat Recovery | |
2 Pre Jan 2004 | 2/5/2003 | Withdrawn | Kittitas County | 182 MW | 182 MW | 瀑布-岩石到达230千伏线路 | 11/14/2004 | Wind | |
1 Pre Jan 2004 | 2/5/2003 | Accepted | Kittitas County | 200 MW | 200 MW | IP Line | 11/14/2004 | Wind | |
3 Pre Jan 2004 | 8/19/2003 | Withdrawn | Kittitas County | 180 MW | 180 MW | 瀑布-岩石到达230千伏线路 | 11/15/2004 | Wind |
*PSE保留所有研究5年. 根据PSE的CEII程序提供研究报告.
**对Colstrip传输系统的请求根据Colstrip传输协议进行管理,其中互连研究将由西北大学进行. See ER11-4636
5/2020 rev